Archive for January, 2010

Leased Line customer access router issues

Friday, January 29th, 2010

Some leased line customers may be experiencing problems with connectivity, due to an issue with an access router.

NewNet engineers are currently investigating to restore service to this router as soon as possible.

Hosted Exchange Maintenance - Saturday 30th January, 06:30 - 08:00

Thursday, January 28th, 2010

NewNet would like to inform you that there will be scheduled maintenance for our Hosted Exchange services between 06:30 to 08:00 on Saturday 30th January. During this time, there will be intermittent access to the hosted exchange services.

We would like to apologise in advance for any inconvenience this may cause.

Emergency ADSL pipe rebalance - 20/01/10, 18:30

Wednesday, January 20th, 2010

Following the loss of a tunnel on one of the BT central pipes overnight, NewNet engineers will be re-balancing the pipes during an emergency maintenance slot on 20/01/10 - 18:30.  All IPStream sessions will be disconnected as a result of this  maintenance, but should re-connect automatically.  If your session does not re-connect automatically, please try power cycling your ADSL modem/router.  If you still have no connection following this, please contact NewNet’s support team.

Anyone who is experiencing issues before the re-balance at 18:30 should attempt disconnecting and re-connecting their PPP session (Power cycling their ADSL router/modem).  This may need to be attempted a couple of times before the session is established on an unaffected pipe.

Hosted Exchange issue - 18/01/2010

Monday, January 18th, 2010

NewNet are currently experiencing loss of connectivity to their Hosted Exchange platform, this is currently being investigated and will be resumed as soon as possible. We apologise for any inconvenience this may be causing.

Planned Maintenance 26/01/2010

Monday, January 18th, 2010

Reason for maintenance – Tuesday 26th January 2010

Window:         Tuesday 26th January 00.01 – 04.00
Description:    Maintenance to core network
Risk assessment:    No expected loss of service

NewNet engineers will be carrying out essential maintenance on routers within the core network to upgrade the network for future expansion.  During this maintenance period engineers will be increasing MTU values on routers to enable Jumbo Frames to pass through the network.